Construction Phasing and Schedule


CONSTRUCTION PHASING

Phase 1 (Fall 2023 - Fall 2024)


UNDER CONSTRUCTION 

     

  • Replace half of the bridge over Norfolk Southern rail lines
  • Reconstruct north side of Ridge Pike from Belvoir Road to Industrial Way
  • Rehab center of I-476 and Plymouth Creek bridges
  • Install new sanitary and storm drainage lines

Phase 2 (Fall 2024 - Summer 2025)

     

  • Replace half of the bridge over Norfolk Southern rail lines
  • Reconstruct south side of Ridge Pike from Belvoir Road to Regal Drive
  • Improve northeast quadrant of Alan Wood Road intersection
  • Rehab north side of I-476 and Plymouth Creek bridges
  • Modify ramps connecting to I-476

Phase 3 (Summer 2025)

     

  • Reconstruct north side of Ridge Pike from Industrial Way to Alan Wood Road
  • Remove Alan Wood Road jughandle
  • Install center median at I-476 and Plymouth Creek bridge area

Phase 4 (Fall 2025)

     

  • Reconstruct center area of Ridge Pike from Carland Road to Regal Drive
  • Install center median approaching Alan Wood Road

Phase 5 (Fall 2025)

  • Place final wearing surface and line striping throughout the project area